Passat mounted part of the LK-1400 belt conveyor on 2RU
Passat mounted part of the LK-1400 belt conveyor at the 2rd Production Unit Belaruskali, JSC. The second oval line has been put into operation. The length of the LC is 1400-320 meters.
Passat specialists are assembling parts of the new conveyor on the third dump line. The length of this conveyor is 290 meters. The length of this conveyor is 290 meters. The platforms for dumper No. 3 are being prepared.
The preparation of the salt dump bed and the strengthening of the dam slopes are being completed. New pumping stations for pressing and drainage salt liquors are being prepared for launch.

Passat specialists install insulated three-layer reinforced concrete and lightweight building structures made of stainless sandwich panels in the tower copra 4RU of JSC Belaruskali. The installation is completed by 20%.

The non-destructive testing laboratory of Passat LLC, Soligorsk, has been accredited and received a certificate confirming compliance with the requirements of ISO / IEC 17025-2019 and is accredited in the field of magnetic control of metal structures and special assemblies self-propelled rolling stock.